Sunday, October 17, 2010

WEEK 22 & 23 - 10/3/10 - 10/16/10

We have completed most of the concrete retaining wall. All exterior concrete will be complete next week. Irrigation/landscape is scheduled to start the week of 10/25. We have started installing the light fixtures, plumbing fixtures, and HVAC equipment; MEP contractors will be complete with all their work inside the building the last week of October. The gutters&downspouts, fence, HVAC controls, and drapery will be installed 11/1-11/5.
Retaining Walls



Mechanical Equipment