We have completed the framing. About 80% of the rough electrical and plumbing is already complete. Within the next 5-7 days, our schedule includes: install asphalt shingles, insulate exterior walls and I-joists, drywall mezzanine, and start masrony.
Brick Mock-up (pending final approval)
9-day Weather Forecast
Wednesday, July 21, 2010
Monday, July 12, 2010
WEEK 9 - 7/4/10 - 7/10/10
Monday, July 5, 2010
WEEK 8 - 6/27/10 - 7/3/10
The framing is 95% complete. We have started the MEP roughs in the new addition. The roof has been temporarily dried in. Over the next few weeks we will: install asphalt shingles, start fire sprinkler, and continue with MEP roughs. The brick masonry will also begin around the week of 7/19.