Wednesday, July 21, 2010

WEEK 10 & 11 - 7/11/10 - 7/24/10

We have completed the framing. About 80% of the rough electrical and plumbing is already complete. Within the next 5-7 days, our schedule includes: install asphalt shingles, insulate exterior walls and I-joists, drywall mezzanine, and start masrony.




Brick Mock-up (pending final approval)


9-day Weather Forecast

Monday, July 12, 2010

WEEK 9 - 7/4/10 - 7/10/10

Project is progressing well. We continue with the interior rough work (i.e. MEP roughs). The framing will be complete next week. We hope to start brick and roofing the week of July 19.




9-day Weather Forecast

Monday, July 5, 2010

WEEK 8 - 6/27/10 - 7/3/10

The framing is 95% complete. We have started the MEP roughs in the new addition. The roof has been temporarily dried in. Over the next few weeks we will: install asphalt shingles, start fire sprinkler, and continue with MEP roughs. The brick masonry will also begin around the week of 7/19.





9-day Weather Forecast