Monday, December 20, 2010

WEEK 32 - 12/12/10 - 12/18/10

Completion of the punch list items nears it's end as painting touch-ups and final hardware items are installed. Substantial Completion was achieved this week and Final Completion is scheduled for January 17th. The work of finishing up final punchlist items is underway.
Paint Touchups




Harware
7-Day Weather Forecast

Thursday, December 2, 2010

WEEK 29 - 31 - 11/21/10 - 12/11/10

We are near the end of the project. We have received the Certificate of Occupancy. The past couple weeks have been full of "final touches". New striping for the parking area has been completed. The landscaping has been finished. All trades are complete. Completion of all the punch list items is 99% complete.
Laminate Table Tops
Ceiling Tiles
Painted Access Panels

Signage
ADA Handrailing
Pavement Striping


9-Day Weather Forecast

Monday, November 15, 2010

WEEK 26 - 28 - 10/31/10 - 11/20/10

Project is almost complete. We have a couple weeks left of punch lists and detail. Carpet is installed, landscape complete, and folding partitions are almost done.








9-Day Weather Forecast

Sunday, October 31, 2010

WEEK 24 & 25 - 10/17/10 - 10/30/10

The past few weeks have been busy. We have completed the exterior concrete work and fine grading. The irrigation&landscape will start 11/1. The painting, tile, millwork, electrical, mechanical, plumbing, fire sprinkler, wood floor, etc. is all substantial complete. Carpet is scheduled for 11/1. Folding partitions will be installed the week of 11/15. We will spend the next few weeks fine-tuning the details.


Automatic Door Opener
Wood Floor


Chapel Sound Panels

9-Day Weather Forecast

Sunday, October 17, 2010

WEEK 22 & 23 - 10/3/10 - 10/16/10

We have completed most of the concrete retaining wall. All exterior concrete will be complete next week. Irrigation/landscape is scheduled to start the week of 10/25. We have started installing the light fixtures, plumbing fixtures, and HVAC equipment; MEP contractors will be complete with all their work inside the building the last week of October. The gutters&downspouts, fence, HVAC controls, and drapery will be installed 11/1-11/5.
Retaining Walls



Mechanical Equipment
Interior Finishes


Sound Deflection Panels
9-Day Weather Forecast

Sunday, October 3, 2010

WEEK 21 - 9/26/10 - 10/2/10

This week we completed the ceramic tile, started installing millwork, and continued with MEP trim-out. We have started working on the exterior concrete and should finish next week. The irrigation is scheduled to start the week of 10/11. The HVAC equipment start-up will be complete next week. Wood floor material is to be delivered the middle of the month.











9-Day Weather Forecast