Sunday, September 5, 2010

WEEK 17 - 8/29/10 - 9/4/10

This week we started drywall tape&bed. Portions of the existing building have been repainted. The EFIS also started this week. Next week we will continue with texturing, painting, and acoustical ceiling tile. The exterior concrete has been delayed some, however, we hope to get that started next week as well. Millwork, wall coverings, and MEP trim-out is scheduled to begin around the middle of September.

I will be out of the office from 9/10 - 9/19. There will be no updates until I return. Thanks.
EIFS
Drywall Tape&Bed

Paint And Ceiling Tile Work On Existing Building