WEEK 14 - 8/8/10 - 8/14/10

We have completed over 90% of the masonry, MEP roughs, and fire sprinkler. Next week we will install the suspended ceiling grid so we can run the ceiling roughs. Final grading and site concrete is scheduled to start on August 18. Sheetrock and tape&bed will begin the week of August 22.

Fire Sprinkler
HVAC Rough

Retractable Stairs
9-Day Weather Forecast