Wednesday, July 21, 2010

WEEK 10 & 11 - 7/11/10 - 7/24/10

We have completed the framing. About 80% of the rough electrical and plumbing is already complete. Within the next 5-7 days, our schedule includes: install asphalt shingles, insulate exterior walls and I-joists, drywall mezzanine, and start masrony.