Friday, May 28, 2010

WEEK 3 - 5/24/10 - 5/28/10

This week we completed excavation of the building pad and passed the required soil tests. We have now started importing the select fill for the building pad. We will trench and pour the footings next week. We have scheduled the rough plumbing and electrical for the following week.