Monday, November 15, 2010
WEEK 26 - 28 - 10/31/10 - 11/20/10
Project is almost complete. We have a couple weeks left of punch lists and detail. Carpet is installed, landscape complete, and folding partitions are almost done.


Sunday, October 31, 2010
WEEK 24 & 25 - 10/17/10 - 10/30/10
The past few weeks have been busy. We have completed the exterior concrete work and fine grading. The irrigation&landscape will start 11/1. The painting, tile, millwork, electrical, mechanical, plumbing, fire sprinkler, wood floor, etc. is all substantial complete. Carpet is scheduled for 11/1. Folding partitions will be installed the week of 11/15. We will spend the next few weeks fine-tuning the details.


Sunday, October 17, 2010
WEEK 22 & 23 - 10/3/10 - 10/16/10
We have completed most of the concrete retaining wall. All exterior concrete will be complete next week. Irrigation/landscape is scheduled to start the week of 10/25. We have started installing the light fixtures, plumbing fixtures, and HVAC equipment; MEP contractors will be complete with all their work inside the building the last week of October. The gutters&downspouts, fence, HVAC controls, and drapery will be installed 11/1-11/5.
Retaining Walls
Sunday, October 3, 2010
WEEK 21 - 9/26/10 - 10/2/10
This week we completed the ceramic tile, started installing millwork, and continued with MEP trim-out. We have started working on the exterior concrete and should finish next week. The irrigation is scheduled to start the week of 10/11. The HVAC equipment start-up will be complete next week. Wood floor material is to be delivered the middle of the month.




Sunday, September 26, 2010
WEEK 18-20 - 9/5/10 - 9/25/10
The construction is progressing well. We have completed the painting, acoustical ceiling tile, and wall coverings. We have started the ceramic tile, exterior concrete, and MEP trim-out. Next week we will complete the ceramic tile, start finish carpentry, and continue MEP trim-out (i.e. installing devices, fixtures, grills, etc.). Exterior concrete should finish the first week of October. Irrigation is scheduled to start the week of October 11.

Retaining Wall

Interior Finishes


Millwork Material
9-Day Weather Forecast

Retaining Wall
Interior Finishes

Millwork Material
9-Day Weather Forecast
Sunday, September 5, 2010
WEEK 17 - 8/29/10 - 9/4/10
This week we started drywall tape&bed. Portions of the existing building have been repainted. The EFIS also started this week. Next week we will continue with texturing, painting, and acoustical ceiling tile. The exterior concrete has been delayed some, however, we hope to get that started next week as well. Millwork, wall coverings, and MEP trim-out is scheduled to begin around the middle of September.
I will be out of the office from 9/10 - 9/19. There will be no updates until I return. Thanks.
EIFS
Drywall Tape&Bed
I will be out of the office from 9/10 - 9/19. There will be no updates until I return. Thanks.
EIFS
Drywall Tape&Bed