The construction is progressing well. We have completed the painting, acoustical ceiling tile, and wall coverings. We have started the ceramic tile, exterior concrete, and MEP trim-out. Next week we will complete the ceramic tile, start finish carpentry, and continue MEP trim-out (i.e. installing devices, fixtures, grills, etc.). Exterior concrete should finish the first week of October. Irrigation is scheduled to start the week of October 11. Retaining Wall Interior Finishes