This week we completed the ceramic tile, started installing millwork, and continued with MEP trim-out. We have started working on the exterior concrete and should finish next week. The irrigation is scheduled to start the week of 10/11. The HVAC equipment start-up will be complete next week. Wood floor material is to be delivered the middle of the month.