This week we started drywall tape&bed. Portions of the existing building have been repainted. The
EFIS also started this week. Next week we will continue with
texturing, painting, and acoustical ceiling tile. The exterior concrete has been delayed some, however, we hope to get that started next week as well.
Millwork, wall coverings, and
MEP trim-out is scheduled to begin around the middle of September.
I will be out of the office from 9/10 - 9/19. There will be no updates until I return. Thanks.EIFS