We have completed the framing. About 80% of the rough electrical and plumbing is already complete. Within the next 5-7 days, our schedule includes: install asphalt shingles, insulate exterior walls and I-joists, drywall mezzanine, and start masrony. Brick Mock-up (pending final approval) 9-day Weather Forecast