We started the rough carpentry on 6/22. The framing is approximately 95% complete. Next week we begin the electrical, HVAC, and plumbing roughs. We are in the process of making some design changes to the fire sprinkler system; should start installation the end of next week. The asphalt shingles are scheduled for 7/12. Roof Trusses HVAC Duct Material 9-day Weather Forecast