WEEK 15 & 16 - 8/15/10- 8/28/10
We have completed install of the ceiling grid and all drywall. Next week we will begin drywall tape&bed, site concrete, and demo of ceiling tile in existing building. EIFS and Tile are scheduled to start towards the middle of September.


Monday, August 16, 2010
WEEK 14 - 8/8/10 - 8/14/10
Monday, August 9, 2010
WEEK 13 - 8/1/10 - 8/7/10
This week we started the masonry, insulation, and sheetrock. By end of next week we hope to have finished: masonry, MEP rough-ins, and fire sprinkler system for new addition. The building should be ready for full sheetrock the week of 8/16. Final grading and site concrete is scheduled to start the week of 8/16.




9-Day Weather Forecast




9-Day Weather Forecast

Sunday, August 1, 2010
WEEK 12 - 7/25/10 - 7/31/10
This week we completed installing the building wrap, windows, and roofing. We also started portions of the insulation and drywall. Next week we will start the brick and continue with the mechanical, plumbing, electrical, and fire sprinkler rough work. Our schedule shows us completing the drywall towards the end of August.