The Big Spring Additional project is complete. We appreciate the efforts of all the the team members who helped make this such a success: Architect, LDS PM, Church Leaders, Subcontractors, and the efforts of the local LDS Church members. The project was completed 33 days early. We look forward to the next one.
Completion of the punch list items nears it's end as painting touch-ups and final hardware items are installed. Substantial Completion was achieved this week and Final Completion is scheduled for January 17th. The work of finishing up final punchlist items is underway. Paint Touchups
We are near the end of the project. We have received the Certificate of Occupancy. The past couple weeks have been full of "final touches". New striping for the parking area has been completed. The landscaping has been finished. All trades are complete. Completion of all the punch list items is 99% complete. Laminate Table Tops
Project is almost complete. We have a couple weeks left of punch lists and detail. Carpet is installed, landscape complete, and folding partitions are almost done.
The past few weeks have been busy. We have completed the exterior concrete work and fine grading. The irrigation&landscape will start 11/1. The painting, tile, millwork, electrical, mechanical, plumbing, fire sprinkler, wood floor, etc. is all substantial complete. Carpet is scheduled for 11/1. Folding partitions will be installed the week of 11/15. We will spend the next few weeks fine-tuning the details.
We have completed most of the concrete retaining wall. All exterior concrete will be complete next week. Irrigation/landscape is scheduled to start the week of 10/25. We have started installing the light fixtures, plumbing fixtures, and HVAC equipment; MEP contractors will be complete with all their work inside the building the last week of October. The gutters&downspouts, fence, HVAC controls, and drapery will be installed 11/1-11/5.