Sunday, September 26, 2010

WEEK 18-20 - 9/5/10 - 9/25/10

The construction is progressing well. We have completed the painting, acoustical ceiling tile, and wall coverings. We have started the ceramic tile, exterior concrete, and MEP trim-out. Next week we will complete the ceramic tile, start finish carpentry, and continue MEP trim-out (i.e. installing devices, fixtures, grills, etc.). Exterior concrete should finish the first week of October. Irrigation is scheduled to start the week of October 11.

Retaining Wall

Interior Finishes



Millwork Material
9-Day Weather Forecast

Sunday, September 5, 2010

WEEK 17 - 8/29/10 - 9/4/10

This week we started drywall tape&bed. Portions of the existing building have been repainted. The EFIS also started this week. Next week we will continue with texturing, painting, and acoustical ceiling tile. The exterior concrete has been delayed some, however, we hope to get that started next week as well. Millwork, wall coverings, and MEP trim-out is scheduled to begin around the middle of September.

I will be out of the office from 9/10 - 9/19. There will be no updates until I return. Thanks.
EIFS
Drywall Tape&Bed

Paint And Ceiling Tile Work On Existing Building

9-Day Weather Forecast